At a Glance

$20.5MTotal FF&E value received, warehoused & installed
2.34M lbsTotal weight handled
117Manufacturers coordinated
820+Guestrooms across 18 floors
17Distinct FF&E categories — guestroom, public area & convention center

“EcoMovers FF&E project snapshot — Omni Hotel & Convention Center.”


The Project

Omni Hotel & Convention Center is a full-scope luxury hospitality build — guestrooms, public spaces, and a major convention center under one envelope. EcoMovers was brought in to receive, warehouse, and install every piece of FF&E across the property.

That meant 820+ guestrooms across 18 floors (roughly 46 keys per floor). The entire public-area program — lobby, lobby cafe, lower and upper lounges, sports bar, all-day dining, Mangrove Restaurant, rooftop bar, spa, fitness center, pool and cabanas. And the full convention center — Grand Ballroom, Junior Ballrooms, Executive Boardroom, Greenroom, prefunction, meeting rooms, and admin suites.

Seventeen distinct FF&E categories. One general contractor. One install team. One point of accountability.

“Omni Hotel & Convention Center — full-scope FF&E installation project by EcoMovers.”


What Was On The Truck

Across the project, we received, staged, and installed every furniture category typical of a luxury hospitality build — guestroom and public area combined.

CategoryProject ValueRepresentative Items
Casegoods$7.55MGuestroom closet & mini-bar units (Type A/A.1/B/B.1/C, left & right configs), desks (left/right/ADA), consoles, side & coffee tables, communal tables
Seating$3.59MDining chairs, lounge chairs, bar stools, banquettes, sectionals (guestroom + restaurant), VPS/PS suite seating
Carpet & Pad$2.62MRoyal Thai, Milliken, Interface broadloom + pad across guestroom and public areas
Wallcovering$1.26MAccent wallcovering across meeting rooms, ballrooms, fitness center
Outdoor Furniture$1.14MAkula sectionals, JANUS et Cie, Kettal pool cabanas, terrace bar stools & lounge chairs
In-Room Lighting$999KTable lamps, desk lamps, sconces, accent chandeliers, bath chandeliers @ VPS/PS
Mirrors$904KAccent, full-length, kitchenette, restroom — guestroom and public area
Accessories$789KLanterns, planters, decorative objects, statues, bird sculptures
Art$596KKevin Barry Fine Art program — Mangrove ceiling feature, Feather Tree sculpture, framed art throughout
OFCI Lighting$536KPreciosa crystal chandeliers (Grand Ballroom, Junior Ballrooms, Prefunction, Reception), custom pendants, restroom vanity lights
Lighted Mirrors$417KMunnWorks back-lit mirrors — guestroom and public restrooms
Area Rugs$61KLoloey hand-knotted rugs in lobby and lounges
Window TreatmentsincludedMecho shades, sheer & solid drapery (Kenco Hospitality)
Pillows & Fabric$31KCustom upholstery pillows for sectionals, banquettes, sofas

Alt text: “Finished luxury guestroom at Omni Hotel & Convention Center — FF&E installation by EcoMovers.”


Field Modification: Because Plans Meet Reality

Specs and as-built rarely match perfectly. On a project this scale, a meaningful portion of the scope required field modification — and that’s a capability we plan for from the receiving stage forward.

Guestroom closet & mini-bar units shipped slightly oversized for as-built room conditions. Across 600+ units, our install crews modified pieces on the floor — closet to closet, room to room — and brought every one in to spec.

VPS and PS suite casegoods — consoles, sectionals, dining chairs at the executive suites — required tighter fit-up tolerances and protective handling. We staged a dedicated suite-level install path so the highest-value pieces moved through the property under controlled conditions.

Public-area dining tables at Mangrove, all-day dining, and the sports bar included custom-built communal tables. We coordinated directly with the millworker for on-site assembly so the tables landed in their final position with no rework.

Convention center built-ins — boardroom conference table, lecterns, bar-height community tables on casters — required final fit-up after wall surfaces were complete. We sequenced our install behind the GC’s wall finishes so nothing got installed twice.

“EcoMovers install in guestroom at Omni Hotel & Convention Center.”


Engineered Handling: The Oversized & Specialty Pieces

Some pieces require more than standard FF&E logistics. Here’s what required engineered handling on this project:

ItemQtyWhy It Required Extra Care
Preciosa Grand Ballroom Chandelier1Largest single fixture on the project — engineered rigging plan and white-glove handling
Preciosa Prefunction Chandelier1700 lbs single fixture; ceiling-coordinated install with the GC
Preciosa Junior Ballroom Chandeliers (L & R)2Mirror-image suspended fixtures hung in tandem
Preciosa Reception Chandelier1Lobby focal piece — installed after surrounding millwork was complete
Kevin Barry “Feather Tree” Sculpture1Multi-piece sculptural assembly — rooftop bar focal point
Kevin Barry Mangrove Ceiling Feature1Ceiling-mounted art installation, restaurant
Kettal Pool CabanasmultiOversized outdoor structures requiring crane and coordinated terrace access
Mangrove Outdoor Sectionals (L + R)2275 lbs each, multi-piece terrace assembly
Guestroom Closet & Mini-Bar Millwork600+Oversized casegoods requiring on-site modification
VPS / PS Suite Sectional Sofas18Oversized seating requiring multi-handler stair/elevator carries
Banquettes (sports bar, dining, breakrooms)20+Up to 550 lbs per unit; rigged through service paths
Shuffleboard table, oval communal table3425 lbs each — convention center and hospitality suite

Extra-care line items on this project included:


When Things Go Sideways: The Water Event

Mid-project, a wing of guestrooms — floors 11 through 29 — sustained a multi-floor water intrusion event.

The kind of thing every GC dreads. The kind of thing that can take a project off schedule and turn the FF&E install into a claims headache.

Here’s what our team did:

  1. De-installed every affected piece in the impacted wing
  2. Wrapped and edge-protected each item for transport
  3. Shuttled to off-site warehouse and tracked condition in storage
  4. Stayed in lockstep with remediation — our schedule moved when their schedule moved
  5. Re-installed every piece as rooms came back online, with no damage claims and no delay to the install sequence in unaffected wings

The remediation team kept their pace. The owner kept their opening sequence. The furniture came back in the same condition it went out.

That’s the difference between an installer and a partner.

“EcoMovers warehouse storage of wrapped FF&E during water remediation at Omni Hotel & Convention Center.”


How We Executed

Receiving. 53-foot trailers staged at the loading dock. Every box destination-coded and routed for streamlined floor flow.

Vertical lift. Every box moved by elevator to the correct floor. When elevators went out of service, we adjusted the install plan that day so unboxing and punch work continued without losing schedule.

Per-floor flow. Helpers unbox to room while installers begin set-and-place behind them. The two crews move together; the floor finishes together.

Salvage and recovery. De-install, wrap, warehouse, and reinstall as remediation schedules allowed.

Punch and follow-up. Post-GC walkthrough corrections. Late-delivery installs. Remediation of artwork installed by other trades. Whatever closed out the punch list, closed out the punch list.

“EcoMovers FF&E receiving and floor-by-floor installation process at Omni Hotel & Convention Center.”


Manufacturer Partners

Across 117 vendors, the names on this project’s BOL reflect the standard of the build:

If your project includes these names — or this caliber of partner — we’ve handled them.


In Their Own Words — Project Highlights

Over $20M of FF&E across 17 categories — from $645 guestroom dining chairs to a $558K Preciosa ballroom chandelier — received, warehoused, and installed under one roof.

Custom millwork on 600+ guestroom closet and mini-bar units — modified on the floor, installed to spec, day after day, room after room.

When a multi-floor water event hit the property, we de-installed, wrapped, and warehoused affected pieces while remediation continued — and put them back when the building was ready.


Have a Project Like This? Let’s Talk.

If you’re planning a hospitality build — luxury hotel, resort, convention property, or mixed-use — and you need an FF&E partner who can handle receiving, warehousing, install, and the things nobody schedules for (water events, oversized pieces, on-site modifications, vendor claims) — that’s what we do.

Book a Project Consult →

A 30-minute call. Walk us through your scope and your timeline. We’ll tell you exactly where and how we can plug in.

Leave a Reply

Your email address will not be published. Required fields are marked *